Deformation Control of Pile Foundations under Subway Tunnel Side-crossing Based on Segmented Deep-hole Grouting: Shenyang Metro Line 3
Yan-feng LI , Yan-ao LIU , Jia-long LI , Feng-yuan WU
Science Technology and Engineering ›› 2025, Vol. 25 ›› Issue (33) : 14414 -14424.
In order to study the deformation control issues when urban metro tunnel construction crosses adjacent pile foundations, ensuring the safety and stability of the pile foundation and its superstructure, a segmented deep-hole grouting reinforcement scheme was used to investigate the actual engineering conditions of a double-line tunnel crossing a nearby overpass. The results show that the vertical maximum grouting reinforcement rates of the ramp bridge, roundabout bridge, and overpass bridge pile foundations are 33.50%, 40.71%, and 73.51%, respectively, while the horizontal maximum grouting reinforcement rates are 54.03%, 56.31%, and 60.82%, respectively. It is concluded that the segmented deep-hole grouting reinforcement scheme effectively reduces both vertical and horizontal deformation of pile foundations, and the crown + pile perimeter grouting reinforcement scheme can effectively control pile foundation deformation during close-proximity tunnel construction.
shallow-buried excavation method / double-line tunnel / existing pile foundation / deep hole grouting
/
| 〈 |
|
〉 |