Settlement Laws of Guiyang Metro Shield Tunnel Passing through High-speed Railway

Chao YANG , Yuan-ming LIU , Kai LIU , Mao-liang TIAN , Jia-jun CHENG , Zhong-xing WANG

Science Technology and Engineering ›› 2025, Vol. 25 ›› Issue (5) : 2100 -2110.

PDF
Science Technology and Engineering ›› 2025, Vol. 25 ›› Issue (5) : 2100-2110 DOI: 10.12404/j.issn.1671-1815.2308729
research-article
Settlement Laws of Guiyang Metro Shield Tunnel Passing through High-speed Railway
Author information +
History +
PDF

Abstract

The construction of the shield tunnel for the high-speed railway will impact the settlement of railway tracks, roadbeds, and other structures, potentially affecting the railway's operation. In order to study the influence of shield tunnel underneath the high-speed railroad in Guiyang area on the settlement pattern of frame box culvert, roadbed and high-speed railway track and the shield construction parameters suitable for Guiyang area, relying on Guiyang Rail Transit Line 3, the model of soil layer-frame culvert-roadbed-track was established to analyze the settlement law of shield construction in limestone on frame culvert, existing high-speed railroad track and roadbed, and to optimize the parameters of shield construction. The results indicate that the settlement of the frame culvert exhibits a "W" shaped transverse and longitudinal settlement pattern, with a peak settlement value of 1.805 mm during the tunneling process. The shield machine's crossing causes a sudden change in subgrade settlement, with the peak value reaching 1.753 mm. High-speed rail track settlement shows a single peak with excavation, with a peak value of 1.41 mm. Analysis of eight types of shield tunneling pressure and grouting pressure reveals that grouting pressure has a better control effect on settlement than excavation pressure. Increasing grouting pressure leads to a decrease in the peak value of subgrade surface settlement, with the peak value reaching 1.355 mm at 800 kPa grouting pressure. The maximum deformation rate is 20.7%, with grouting pressure set at 800 kPa and tunneling pressure at 100 kPa for the shield machine.

Keywords

shield tunnel / settlement / frame bridge culvert / railroad track / roadbed / shield parameters

Cite this article

Download citation ▾
Chao YANG, Yuan-ming LIU, Kai LIU, Mao-liang TIAN, Jia-jun CHENG, Zhong-xing WANG. Settlement Laws of Guiyang Metro Shield Tunnel Passing through High-speed Railway. Science Technology and Engineering, 2025, 25(5): 2100-2110 DOI:10.12404/j.issn.1671-1815.2308729

登录浏览全文

4963

注册一个新账户 忘记密码

References

Funding

PDF (16694KB)

19

Accesses

0

Citation

Detail

Sections
Recommended

/

〈 〉