Influence Law and Control Measures of Shield Tunnel Undercrossing High Speed Railway Station: Taking the Tianjin Metro Line 4 as an Example of Undercrossing Tianjin West Station

Sheng-zhang HAN , Ye-tao JI , Lin-song ZHAO , Ying LIU , Zhao-rong XU , Ling-bo MENG , Xue-song CHENG

Science Technology and Engineering ›› 2024, Vol. 24 ›› Issue (31) : 13601 -13611.

PDF
Science Technology and Engineering ›› 2024, Vol. 24 ›› Issue (31) : 13601-13611 DOI: 10.12404/j.issn.1671-1815.2304736
research-article
Influence Law and Control Measures of Shield Tunnel Undercrossing High Speed Railway Station: Taking the Tianjin Metro Line 4 as an Example of Undercrossing Tianjin West Station
Author information +
History +
PDF

Abstract

There is insufficient research on the deformation laws and construction measures of the underpass high-speed railway station project. Taking the Tianjin Metro Line 4 North Section undercrossing Tianjin West Station project as the background, and using large-scale finite element software to conduct numerical simulation of the undercrossing project, the effectiveness of various construction measures was verifyied, and the deformation of the pile foundation was analyzed. Results show that the filling and grouting construction of the gaps around the shield and the secondary grouting construction have a good effect on reducing ground settlement. Thickening the bottom plate can reduce the vertical deformation of the shield tunneling structure to a certain extent. and the frame structure of the station building itself reduces the impact of shield tunneling to a certain extent. The greater the pressure on the palm face, the greater the lateral displacement of the upper part of the pile foundation away from the shield tunneling, and the greater the displacement towards the direction of the shield tunneling. The greater the grouting pressure, the smaller the lateral and longitudinal deformation of the pile foundation. During the process of shield tunneling, the top of the pile foundation is constantly sinking, while the bottom is slightly raised. The research results can provide reference and reference for similar projects such as shield tunneling through existing underground structures.

Keywords

shield tunneling / high speed railway stations / construction measures / numerical simulation

Cite this article

Download citation ▾
Sheng-zhang HAN, Ye-tao JI, Lin-song ZHAO, Ying LIU, Zhao-rong XU, Ling-bo MENG, Xue-song CHENG. Influence Law and Control Measures of Shield Tunnel Undercrossing High Speed Railway Station: Taking the Tianjin Metro Line 4 as an Example of Undercrossing Tianjin West Station. Science Technology and Engineering, 2024, 24(31): 13601-13611 DOI:10.12404/j.issn.1671-1815.2304736

登录浏览全文

4963

注册一个新账户 忘记密码

References

Funding

PDF (16441KB)

18

Accesses

0

Citation

Detail

Sections
Recommended

/

〈 〉